SPECIFICATION GENERATOR
Find out which low impact materials are right for your building project.
How quickly do I need to get the render on the UdiFRONT system?
Find out more about how we approach this building scenario.
The Diffutherm boards are OK to be left open to the elements for up to 8 weeks. Just make sure that any dirt or loose material is removed from the surface before you apply the UdiFOUNDATION COAT render and that the boards are dry.